If you are planning exterior cladding for your Southery home, here is exactly what the process involves from the initial inspection through to the finished, cleaned-up result.
Call any time. Calls are answered day and night and passed straight to our roofers.
Exterior cladding is not a simple board-swap job. A number of separate stages each need to be done correctly in sequence, and skipping or rushing any of them is what causes new cladding to fail years before it should. We carry out cladding installation and replacement for homeowners across Southery and the wider Downham Market area, and the process below is what a properly done job looks like from start to finish.
Before any work is priced or planned, the existing wall surface needs to be assessed. This means looking at what is currently on the wall - whether that is bare render, existing cladding or bare blockwork - and what condition it is in. For a re-clad, the existing boards and batten frame are inspected for rot, failed fixings and any sign of water ingress behind the boards.
It also means looking at the surrounding details: the condition of window and door frames, any pipes or cables that pass through the wall face, and how the elevation meets the roof line, soffits and fascias. All of these junctions are potential water entry points, and they all need to be incorporated into the cladding design. A quote produced without this inspection is unlikely to be accurate.
Once the inspection is done, we agree the specification with you. This covers the material (timber, composite or fibre cement), the profile and colour, the fixing method, the batten depth, and how all the junction details are going to be handled. This is also when any preparatory work is identified - for example, if window frames need to be made good before cladding goes around them, or if a section of render needs to be hacked off because it has failed.
It is worth spending time on this stage. Changing the material or profile after boards have been ordered usually means delays and, in some cases, a restocking charge from the supplier. Agreeing everything clearly up front avoids that.
Once the specification is agreed, materials are ordered. Lead times vary by material and supplier. Standard composite and fibre cement boards in common colours are often available within a few working days. Timber cladding in specific species or finishes, or composite boards in non-standard colours, can take longer.
On the day work starts, the site is set up with scaffold or access equipment appropriate to the elevation height. Ground-level protection is laid to protect any paving, planting or drainage below the working area. This is basic but important - fibre cement off-cuts and batten timber dropped from height can damage paving and block gulley gratings.
If the job is a re-clad, the old boards come off first. This is done carefully rather than quickly - boards ripped off without care can pull render or masonry with them, creating a bigger repair job than necessary. Once the boards are off, the batten frame is inspected properly for the first time. On older installations it is common to find that the battens closest to ground level, or directly behind any boards that showed signs of rot, need to be replaced.
If the job is a new installation onto bare wall, the wall surface is checked for soundness. Any loose render is removed and the wall is allowed to dry if it has been recently wet. A breather membrane is fixed to the wall face at this stage before battening begins. The membrane allows any moisture that gets behind the boards to escape downwards rather than sit against the masonry.
The batten framework creates the ventilated cavity between the wall and the cladding. A minimum 25mm cavity is standard, though 38mm or 50mm is better on exposed elevations because it improves airflow and gives a clearer drainage path for any water that gets behind the boards.
Battens are fixed to the wall through the membrane into the masonry using appropriate fixings at correct centres - typically no more than 600mm apart vertically. Timber battens should be treated or specified as a durable species. Using untreated softwood battens behind composite or fibre cement boards is a common false economy - the boards may last decades, but the hidden battens can rot within ten years, requiring a full strip-and-re-clad to replace them.
At the top and bottom of the elevation, a ventilation cavity closer or perforated closer strip is fitted to allow airflow while preventing insects from nesting in the gap.
Boards are cut to length and fixed to the batten frame starting from the bottom of the elevation and working upwards. The starter course sits at the correct height above finished ground level - at least 150mm to avoid splash-back from rain hitting hard surfaces. A temporary packing strip or starter batten is often used to set the correct angle for the first course of featheredge or weatherboard profile.
Each board is fixed using stainless steel or hot-dipped galvanised fixings at the correct spacing. Steel fixings rust and cause staining on the board face; they also expand as they corrode and can split the board from inside the fixing hole. This is one area where the difference in material cost is trivial compared to the difference in longevity.
Around windows, doors and any wall penetrations, the boards are cut in carefully and the joints are sealed with a flexible, paintable sealant specified for exterior use. This is detail work that takes time to do properly but is the difference between a cladding installation that stays weathertight for years and one that starts letting water in at the joints within a couple of winters.
The top of the cladding where it meets the soffit or roof verge is one of the most important details on the whole job. Water running down the wall behind the boards needs to be directed away from the building, not into it. A metal or purpose-made flashing is fitted at this junction to direct any water outward.
At internal and external corners, the boards are either mitred, returned or covered with purpose-made corner trim. External corners take a great deal of wind-driven rain, so the jointing here needs to be particularly careful.
Where boards need to be joined along their length - on a long elevation that exceeds the maximum board length - the joints are staggered across courses so they are not all in the same vertical line, and each joint is made over a batten rather than in mid-air.
Fibre cement boards that are supplied primed rather than factory-painted will need a top coat on site. Timber boards that are not pre-treated or pre-stained will need finishing before the scaffold comes down. This stage is easier and produces a better result while the boards are freshly installed and accessible.
Once the boards are up and all details are finished, the elevation is checked from ground level and, where safe to do so, by hand to make sure no fixings are missing or proud, no sealant lines are open, and no boards are sitting out of line. Off-cuts, packaging and any replaced material are removed from site. Ground protection is taken up and the area is left clean.
If you want exterior cladding installed properly in Southery, call Downham Market Roofers and we will come out to assess the job and talk you through what it involves for your specific property.